Project Planning Chart

Keywords planning project planning project planning chart
Standards groups

Requirements:

1. Reference documents. None.
2. Format: The chart shall be in contractor’s format.
3. Content.

3.1 Project planning chart. It shall depict actual and schedules progress for each subdivision using
horizontal lines and symbols. Actual progress will be noted
by a percentage of the completion figure.

3.2 Progress of work. Subsequent additions to the work breakdown shall be made as
they occur in contract work performance. Items shall not be deleted even though work
may be cancelled or stopped before completion.

Metadata
Document identifier
DI-MGMT-80507B
Date published
2006-11-14
Language
English
Document type
Data Item Description (DID)
Pages
3
Defines standard
Replaced/Superseded by document(s)
Cancelled by
Amended by
File MIME type Size (KB) Language Download
Project Planning Chart.pdf application/pdf   231.07 KB English DOWNLOAD!
File attachments
Cover images
Introduction

The Project Planning Chart graphically depicts the schedule and actual progress of work
on a contract.

This Data Item Description (DID) contains format and content preparation instructions
for the data product generated by the specific and discrete task requirement as delineated in the contract.