3.2.1 Milestone/task status. The status of each milestone/task as defined by the
statement of work or contract, as applicable:
a. A statement as to whether or not the program/project/task is on schedule; if
not, the effort planned to meet the schedule shall be indicated. Include an
overall status of each milestone, task, or unit of work. Include update schedule
sheets, milestone charts, or task synopsis sheets identifying phase of task and
percentage of completion of each task, technical instruction, or order.
b. A comparison of achieved end-product performance capabilities projected
against contract baseline values, requirements, or allocations.
c. Effort expended on each task to date, and a brief description of technical
developments and accomplishments.
d. Key dates in any testing program and description of tests performed and
significant test results. If applicable, a description of the amount and type
of down time on the equipment or system under test.
e. A list of all designs completed and a brief description of each item. For
designs in process, provide estimated dates for design and drawing
completion.
Defines standard
Replaced/Superseded by document(s)
Cancelled by
Amended by
File | MIME type | Size (KB) | Language | Download | |
---|---|---|---|---|---|
Status Report.PDF | application/pdf | 234.23 KB | English | DOWNLOAD! |
Provides definitions
Introduction
The Status Report documents the status of contractor effort towards achieving contract
objectives. It identifies accomplishments to date and difficulties encountered, and compare the status achieved to planned goals and the resources expended. It is used by the Government to monitor and evaluate contractor performance.